| Location | Activity Description | Unit | Planned Qty | Completed Qty | % Complete | Remarks | | :--- | :--- | :--- | :--- | :--- | :--- | :--- | | | Soil Stack Installation | No. | 8 | 8 | 100% | Pressure test passed | | Level 4 | Rain Water Pipe (RWP) | LM | 120 | 95 | 79% | On track | | Roof | Condensate drain piping | LM | 200 | 140 | 70% | Waiting for HVAC tray alignment | | BOH | Water Heater connection | Set | 2 | 0 | 0% | Starts Oct 25 |
If you want this tailored to a different project type, format (weekly/fortnightly), or as an editable Word/Excel template, tell me which and I’ll produce it. mep work progress report sample